Project Duration
Start Date: Apr.- 2013
Completion Date: Aug. – 2018
Project Value 144.0 (Million KD)
Project (1): Sheikh Jaber Al Sabah Highway – Agreement No. 62/4
Location: SJAS Highway – Alba & Nuwaidrat Intersections
Project Stages
|
2. Construction of Phase 2 – Main Works |
3. Supervision Consultancy services for Phase 1 & Phase 2 works |
4. Design Services to upgrade App. 9.5 KM |
Project (2): Tubli Treatment Plant – Agreement No. 62/5
Location: Tubli
Project Stages
|
2.Construction of Tubli Sewer Treatment Plant Expansion Phase 04 |
Project (3): North Road Leading To North City – Agreement No. 62/6
Location: North Road Leading to North City
Project Works
|
2. Construction of Jasrah Interchange Upgrade Phase 1 Package-0 (B) |
3. Construction of Jasra Grade Separated Junction Reconfiguration-Pkg. 1 B-Stage 2A & 2B |
4. Construction of W-Link Package-1A |
5. Supervision Consultancy services for W-Link Package-1A |
6. Design for Budaiya & Janabiya Hiway Upgrade-Package-3 |
7. Design & Supervision for widening of SIBS Hwy & Jasra Interchange upgrade Ph -2 Package 4 |
Project Value: Three Main Projects with a total budget 470 M.$